Steering
Thursday, Oct 22. The plant two and plant three cutover decisions are taken here. The pack reaches you two days before.
- Plant two cutover go or no-goNeeds the plant two report on trained super users, due Oct 8.Your decision
- Plant three cutover dateOpen 15 days. Super user training waits for it.Your decision
- Collections statusUnchanged for two cycles. Claire takes it to steering if the blocking item is still unnamed.At risk
- Benefits readingsTwo benefits not measured; the cycle time baseline for plants two and three is being captured.