Benefits

An unmeasured benefit is never counted as realized. A change with another cause is recorded as observed.

Benefits review, updated Oct 1, 2026
A finance and operations team reviewing measured benefits

Due for measurement

Thornbury order-to-cash program 2 benefits not measured Observed, not attributed

Each benefit claimed at scoping, set beside what has been measured since go-live, including the benefits that were never measured. It is the basis on which the next phase is discussed, and an unmeasured benefit is never counted as realized. Prepared by Claire Dubois, engagement partner at Corbel Partners, with Tom Becker, PMO lead, for Robert Lang, chief operating officer at Thornbury Components and program sponsor. Record as of Thursday, October 1, 2026, with readings dated September 15 to September 30. Every latest value is a reading from the client's own source named in the register. No figure on this page is modeled or forecast, and each target is a goal agreed at scoping, not a prediction.

Invoice disputes a month at plant one41down from 64 at May 31; target under 30
Thornbury claims with a baseline14of 17 on the register
Realized2re-keys and order entry error rate
Not measured2cycle time at plants two and three, manual journals

Claims due for measurement fall into two groups: Baseline set claims need their first reading and Measuring claims their next reading, on the dates in the measurement plan. Claims without a baseline appear in the claims table with what was never measured.

Live from the Dashboards appOpen the full report

Claims against measurements

These are the Thornbury claims that have a reading or a stated gap. Dates in brackets are the baseline date and the date of the latest reading.

Benefit claimedBaselineTargetLatest readingStatusBenefit owner
Fewer invoice disputes at plant one64 a month (May 31)Under 30 a month41 (Sep 30)MeasuringSunita Rao
Order-to-cash cycle at plant one58 days (May 31)45 days51 days (Sep 30)Partly realizedSunita Rao
Fewer manual order re-keys120 a week (Apr 30)Under 40 a week28 a week (Sep 15)RealizedSunita Rao
Order entry error rate at plants one and two6.4 percent (May 31)Under 2 percent1.8 percent (Sep 25)RealizedRobert Lang
Invoice accuracy at first issue91 percent (May 31)98 percent95.5 percent (Sep 28)Partly realizedSunita Rao
Order desk overtime at plant one95 hours a month (Jun 30)Under 40 a month52 hours (Sep 30)Partly realizedRobert Lang
Receivables over 60 days past due$1,840,000 (May 31)Under $1,200,000$1,530,000 (Sep 30)MeasuringSunita Rao
Month-end close duration9 days (Jul 31)6 working days6 days (Sep 4, one close only)MeasuringSunita Rao
Duplicate customer accounts1,260 (Aug 15)Under 100410 (Sep 28)MeasuringRobert Lang
Invoices issued within two days of shipment, plant one72 percent (May 31)95 percent73 percent (Sep 28)Not realizedSunita Rao
Shorter cycle at plants two and threeNone capturedNo target recordedNoneNot measuredRobert Lang
Manual journal entriesNoneUnder 150 a monthNoneNot measuredSunita Rao

Claims with a baseline set but no reading yet, and one claim with neither:

Benefit claimedStatusBaselineTargetNext reviewBenefit owner
Faster credit hold releaseBaseline set30 hours (Sep 15)Under 8 hoursNov 15Sunita Rao
Billing team overtimeBaseline set210 hours a month (Aug 31)Under 120 a monthDec 31Sunita Rao
Orders waiting over one day at plant twoBaseline set47 a week (Jun 30)Under 10 a weekOct 30Robert Lang
Orders shipped over credit limitBaseline set22 a month (Aug 31)Under 5 a monthNov 2Sunita Rao
Credit notes issued within five daysClaimedNone; the three plants log credit notes in separate spreadsheets90 percentOct 23Sunita Rao
Live from the Dashboards appOpen the full report

Attribution notes

A result is called attributable to the program only when nothing else changed in the same period. Where something did, Claire Dubois records the change as observed and says what else moved.

Two more readings are weaker than they look. The month-end close duration rests on the August close alone: the review set for Sep 28 was not held because the finance controller was away, and finance wants the September quarter-end close before treating the target as met. The duplicate customer account count of 410 is only partly updated, because the plant three duplicate list is still under review.

Live from the Dashboards appOpen the full report

Measurement plan

The cycle time gap closes first. Plants two and three have not yet cut over to the new order-to-cash process, so orders at those plants that are paid between October 1 and October 28 still reflect the old process, and their days from order to cash received can serve as the baseline.

  1. Baselines recorded where data exists: 14 of 17 Thornbury claims
  2. Benefit owner and evidence source named for every claim
  3. Capture the cycle time baseline for plants two and three, orders paid Oct 1 to Oct 28
  4. Reschedule the month-end close review and the journal review that were not held
  5. Measurement reviews, Oct 15 to Oct 31
  6. Benefits review with Robert Lang, Tuesday Nov 17, before any next phase is discussed
Next reviewBenefitReviewed with
Oct 15Shorter cycle at plants two and threeRobert Lang
Oct 20Duplicate customer accountsRobert Lang
Oct 23Credit notes issued within five daysSunita Rao
Oct 30Receivables over 60 days past due; orders waiting over one day at plant twoSunita Rao, Robert Lang
Oct 31Fewer invoice disputes at plant oneSunita Rao
Nov 6Invoices issued within two days of shipmentSunita Rao

How a result is labelled on this page

Observed. The measure moved after go-live and nothing else is known to have changed. It is still reported as a reading, not as proof.

Attributed. Only used when a comparison or a control shows the program caused the change. No result on this page is labelled attributed yet.

Not measured. No baseline or no data exists. It is listed, owned and dated, and never counted as realized.

Who is on this review

  • Robert LangChief operating officer, Thornbury Components, program sponsor

  • Claire DuboisEngagement partner, Corbel Partners, prepared this review

  • Tom BeckerPMO lead, Corbel Partners, keeps the measurement plan