Onboarding
Plant two joins the program's status cycle before its cutover decision at steering on Oct 22.
- Program scopePlant two scope agreed
- Milestones and criteriaReadiness 2 of 4
- GovernanceGo or no-go at steering
- Workstream ownersOrder desk owner to name
Plant two onboarding
The four onboarding steps with every item, owner and date. Tick items off as your teams send them.Program checklist
What plant two needs
Access is requested at the minimum each task needs and recorded here. You can revoke any grant.
| Item | Step | Status |
|---|---|---|
| Plant two scope: order desk, invoicing, credit | Program scope | Agreed |
| Plant two cutover readiness criteria | Milestones and criteria | 2 of 4 evidenced |
| Trained super users at plant two | Milestones and criteria | Report due Oct 8 |
| Go or no-go taken at steering | Governance | Oct 22 |
| Fortnightly status from the plant two lead | Governance | From Oct 14 |
| Plant two stream lead named | Workstream owners | Named |
| Plant two order desk owner | Workstream owners | Waiting on you |